Planters, Medians and Tree Feasibility


  1. 2026
  2. Project Pictures

DECEMBER

Project work progressed across multiple areas throughout the month of December. Along San Bruno and Angus Avenues, investigations identified an abandoned east–west pipe as the likely pathway for water intrusion into the electrical conduit, indicating that the previously approved sleeve solution may not fully resolve the issue and that additional demolition may be required to identify the water source. During December, crews shifted efforts to other tasks, including placing pea gravel and soil in concrete pots along San Mateo Avenue and advancing planting activities. Planters at the San Mateo/Jenevein intersection were completed with irrigation installed, tested, and mulched, and work in Posey Park and the medians was largely completed pending delivery of benches and trash receptacles. Tree planting progressed along San Mateo and Jenevein Avenues, the parking kiosk concrete base was poured and allowed to cure, and site cleanup, compaction, and inspections were completed in preparation for winter rain events.

NOVEMBER

Throughout November, crews made substantial progress across San Mateo Avenue, Jenevein Avenue, and Sylvan Avenue. On San Mateo Avenue, three leaks were repaired and a fourth, more complex leak near the Lotus Restaurant was identified for further investigation, while concrete demolition and soil preparation advanced at the former pot locations near Summer’s Laundry. Along Jenevein Avenue, most curb-line demolition was completed, the parking kiosk was temporarily relocated to allow remaining work, and crews proceeded with grading, root-barrier installation, asphalt removal, and underground irrigation preparation in coordination with WH inspections. At Sylvan Avenue, demolition, pipe locating, and backfilling moved forward on all sides of the intersection, with additional excavation required where utilities were not found as marked. Planting work also progressed, with shrubs delivered and their placement verified at the Jenevein/San Mateo intersection, allowing soil preparation and installation to begin.

OCTOBER

This month, Marina crews began work at Posy Plaza by removing existing plants and the eight benches surrounding the central planter. Work also progressed at the San Mateo Avenue median in front of Posy Plaza, where the team removed old landscaping and irrigation components and began installing a new irrigation system. Soil was removed from the planters in preparation for the new system, and installation efforts are continuing.